Current price for 03.11.2025
1. Eurofence made of concrete slabs, unpainted
Name of work
Unit.
Cost
1.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
1.2. Cleaning of the food supply with rammers
м.п.
100 ₴
1.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
1.4. Formwork installation/dismantling
м.п.
205 ₴
1.5. Manufacturing of reinforcing cage
т
15 000 ₴
1.6. Concreting the foundation
м3
1 400 ₴
1.7. Installation of a fence made of concrete slabs
м.п.
575 ₴
1.8. Concreting of free-standing pillars (if a strip foundation is not being made)
шт
350 ₴
2. Eurofence made of painted concrete slabs
Name of work
Unit.
Cost
2.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
2.2. Cleaning of the food supply with rammers
м.п.
100 ₴
2.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
2.4. Formwork installation/dismantling
м.п.
205 ₴
2.5. Manufacturing of reinforcing cage
т
15 000 ₴
2.6. Concreting the foundation
м3
1 400 ₴
2.7. Installation of a fence made of concrete slabs
м.п.
575 ₴
2.8. Concreting of free-standing pillars (if a strip foundation is not being made)
шт
350 ₴
2.9. Fence primer
м2
35 ₴
2.10. Painting the fence
м2
150 ₴
3. Solid wood
Name of work
Unit.
Cost
3.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
3.2. Cleaning of the food supply with rammers
м.п.
100 ₴
3.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
3.4. Formwork installation/dismantling
м.п.
205 ₴
3.5. Manufacturing of reinforcing cage
т
15 000 ₴
3.6. Concreting the foundation
м3
1 400 ₴
3.7. Installation of a wooden fence
м.п.
750 ₴
3.8. Concreting of free-standing pillars (if a strip foundation is not being made)
шт
350 ₴
3.9. Fence primer
м2
35 ₴
3.10. Painting the fence
м2
150 ₴
4. Made of wood with brick columns
Name of work
Unit.
Cost
4.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
4.2. Cleaning of the food supply with rammers
м.п.
100 ₴
4.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
4.4. Formwork installation/dismantling
м.п.
205 ₴
4.5. Manufacturing of reinforcing cage
т
15 000 ₴
4.6. Concreting the foundation
м3
1 400 ₴
4.7. Installation of a wooden fence with brick columns and installation of a cap on a post
м.п.
1 925 ₴
4.8. Concreting of free-standing pillars (if a strip foundation is not being made)
шт
350 ₴
4.9. Fence primer
м2
35 ₴
4.10. Painting the fence
м2
150 ₴
5. Solid brick
Name of work
Unit.
Cost
5.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
5.2. Cleaning of the food supply with rammers
м.п.
100 ₴
5.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
5.4. Formwork installation/dismantling
м.п.
205 ₴
5.5. Manufacturing of reinforcing cage
т
15 000 ₴
5.6. Concreting the foundation
м3
1 400 ₴
5.7. Laying a brick fence with jointing
м.п.
4 700 ₴
5.8. Installation of covers
шт
350 ₴
6. Made of brick with corrugated sheet filling between columns
Name of work
Unit.
Cost
6.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
6.2. Cleaning of the food supply with rammers
м.п.
100 ₴
6.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
6.4. Formwork installation/dismantling
м.п.
205 ₴
6.5. Manufacturing of reinforcing cage
т
15 000 ₴
6.6. Concreting the foundation
м3
1 400 ₴
6.7. Laying a brick fence with installation of guides for corrugated sheets and installation of corrugated sheets
м.п.
3 600 ₴
6.8. Installation of covers
шт
350 ₴
7. Made of brick with wood filling between columns
Name of work
Unit.
Cost
7.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
7.2. Cleaning of the food supply with rammers
м.п.
100 ₴
7.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
7.4. Formwork installation/dismantling
м.п.
205 ₴
7.5. Manufacturing of reinforcing cage
т
15 000 ₴
7.6. Concreting the foundation
м3
1 400 ₴
7.7. Laying a brick fence with installation of guides for cladding and wood cladding
м.п.
3 600 ₴
7.8. Installation of covers
шт
350 ₴
8. Made of brick with polycarbonate filling between columns
Name of work
Unit.
Cost
8.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
8.2. Cleaning of the food supply with rammers
м.п.
100 ₴
8.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
8.4. Formwork installation/dismantling
м.п.
205 ₴
8.5. Manufacturing of reinforcing cage
т
15 000 ₴
8.6. Concreting the foundation
м3
1 400 ₴
8.7. Laying a brick fence with installation of guides for cladding and polycarbonate cladding
м.п.
3 850 ₴
8.8. Installation of covers
шт
350 ₴
9. Made of brick with rubble filling between columns
Name of work
Unit.
Cost
9.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
9.2. Cleaning of the food supply with rammers
м.п.
100 ₴
9.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
9.4. Formwork installation/dismantling
м.п.
205 ₴
9.5. Manufacturing of reinforcing cage
т
15 000 ₴
9.6. Concreting the foundation
м3
1 400 ₴
9.7. Laying a brick fence with rubble filling between columns
м.п.
4 600 ₴
9.8. Installation of covers
шт
350 ₴
10. Solid rubble stone
Name of work
Unit.
Cost
10.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
10.2. Cleaning of the food supply with rammers
м.п.
100 ₴
10.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
10.4. Formwork installation/dismantling
м.п.
205 ₴
10.5. Manufacturing of reinforcing cage
т
15 000 ₴
10.6. Concreting the foundation
м3
1 400 ₴
10.7. Laying a brick fence with rubble filling between columns
м.п.
4 850 ₴
10.8. Laying a fence from rubble stone
шт
350 ₴
11. Made of rubble stone with brick filling between columns
Name of work
Unit.
Cost
11.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
11.2. Cleaning of the food supply with rammers
м.п.
100 ₴
11.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
11.4. Formwork installation/dismantling
м.п.
205 ₴
11.5. Manufacturing of reinforcing cage
т
15 000 ₴
11.6. Concreting the foundation
м3
1 400 ₴
11.7. Laying a fence from rubble with filling between columns with bricks
м.п.
5 500 ₴
11.8. Installation of covers
шт
350 ₴
12. Made of rubble stone with corrugated sheet filling between columns
Name of work
Unit.
Cost
12.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
12.2. Cleaning of the food supply with rammers
м.п.
100 ₴
12.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
12.4. Formwork installation/dismantling
м.п.
205 ₴
12.5. Manufacturing of reinforcing cage
т
15 000 ₴
12.6. Concreting the foundation
м3
1 400 ₴
12.7. Laying a fence from rubble with filling between columns with corrugated sheets
м.п.
5 800 ₴
12.8. Installation of covers
шт
350 ₴
13. Made of rubble stone with metal grating filling between columns
Name of work
Unit.
Cost
13.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
13.2. Cleaning of the food supply with rammers
м.п.
100 ₴
13.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
13.4. Formwork installation/dismantling
м.п.
205 ₴
13.5. Manufacturing of reinforcing cage
т
15 000 ₴
13.6. Concreting the foundation
м3
1 400 ₴
13.7. Laying a fence from rubble with filling between columns with a metal lattice
м.п.
5 800 ₴
13.8. Installation of covers
шт
350 ₴
14. From a solid decorative block
Name of work
Unit.
Cost
14.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
14.2. Cleaning of the food supply with rammers
м.п.
100 ₴
14.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
14.4. Formwork installation/dismantling
м.п.
205 ₴
14.5. Manufacturing of reinforcing cage
т
15 000 ₴
14.6. Concreting the foundation
м3
1 400 ₴
14.7. Laying decorative block
шт
100 ₴
14.8. Installation of covers
шт
350 ₴
14.9. Reinforcement of columns and longitudinal rows of blocks
м.п.
30 ₴
14.10. Concreting of block voids
м3
1 500 ₴
14.11. Preparing concrete manually
м3
1 500 ₴
15. From a decorative block with brick filling between the columns
Name of work
Unit.
Cost
15.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
15.2. Cleaning of the food supply with rammers
м.п.
100 ₴
15.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
15.4. Formwork installation/dismantling
м.п.
205 ₴
15.5. Manufacturing of reinforcing cage
т
15 000 ₴
15.6. Concreting the foundation
м3
1 400 ₴
15.7. Laying a column from a decorative block with filling between the columns with bricks
м.п.
4 200 ₴
15.8. Installation of covers
шт
350 ₴
15.9. Reinforcement of columns and longitudinal rows of blocks
м.п.
30 ₴
15.10. Concreting of block voids
м3
1 500 ₴
15.11. Preparing concrete manually
м3
1 500 ₴
16. From a decorative block with filling between columns with corrugated sheets
Name of work
Unit.
Cost
16.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
16.2. Cleaning of the food supply with rammers
м.п.
100 ₴
16.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
16.4. Formwork installation/dismantling
м.п.
205 ₴
16.5. Manufacturing of reinforcing cage
т
15 000 ₴
16.6. Concreting the foundation
м3
1 400 ₴
16.7. Laying a column from a decorative block with filling between the columns with bricks
м.п.
3 550 ₴
16.8. Installation of covers
шт
350 ₴
16.9. Reinforcement of columns and longitudinal rows of blocks
м.п.
30 ₴
16.10. Concreting of block voids
м3
1 500 ₴
16.11. Preparing concrete manually
м3
1 500 ₴
17. From a decorative block with filling between columns with rubble
Name of work
Unit.
Cost
17.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
17.2. Cleaning of the food supply with rammers
м.п.
100 ₴
17.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
17.4. Formwork installation/dismantling
м.п.
205 ₴
17.5. Manufacturing of reinforcing cage
т
15 000 ₴
17.6. Concreting the foundation
м3
1 400 ₴
17.7. Laying a column from a decorative block with filling between the columns with rubble
м.п.
5 950 ₴
17.8. Installation of covers
шт
350 ₴
17.9. Reinforcement of columns and longitudinal rows of blocks
м.п.
30 ₴
17.10. Concreting of block voids
м3
1 500 ₴
17.11. Preparing concrete manually
м3
1 500 ₴
18. From a decorative block with filling between the columns with a metal lattice
Name of work
Unit.
Cost
18.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
18.2. Cleaning of the food supply with rammers
м.п.
100 ₴
18.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
18.4. Formwork installation/dismantling
м.п.
205 ₴
18.5. Manufacturing of reinforcing cage
т
15 000 ₴
18.6. Concreting the foundation
м3
1 400 ₴
18.7. Laying a column from a decorative block with filling between the columns with a metal lattice
м.п.
5 950 ₴
18.8. Installation of covers
шт
350 ₴
18.9. Reinforcement of columns and longitudinal rows of blocks
м.п.
30 ₴
18.10. Concreting of block voids
м3
1 500 ₴
18.11. Preparing concrete manually
м3
1 500 ₴
19. From corrugated sheets on metal poles
Name of work
Unit.
Cost
19.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
19.2. Cleaning of the food supply with rammers
м.п.
100 ₴
19.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
19.4. Formwork installation/dismantling
м.п.
205 ₴
19.5. Manufacturing of reinforcing cage
т
15 000 ₴
19.6. Concreting the foundation
м3
1 400 ₴
19.7. Concreting of free-standing pillars (if a strip foundation is not being made)
шт
350 ₴
19.8. Installation of fence guides in 2 rows
м.п.
100 ₴
19.9. Painting the fence
м.п.
150 ₴
19.10. Installation of corrugated sheeting on a fence
м.п.
305 ₴
19.11. Installation of U-shaped strip
м.п.
120 ₴
20. From picket fence on metal poles
Name of work
Unit.
Cost
20.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
20.2. Cleaning of the food supply with rammers
м.п.
100 ₴
20.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
20.4. Formwork installation/dismantling
м.п.
205 ₴
20.5. Manufacturing of reinforcing cage
т
15 000 ₴
20.6. Concreting the foundation
м3
1 400 ₴
20.7. Concreting of free-standing pillars (if a strip foundation is not being made)
шт
350 ₴
20.8. Installation of fence guides in 2 rows
м.п.
100 ₴
20.9. Painting the fence
м.п.
150 ₴
20.10. Installation of picket fence (one side 70% sheathing or 2 sides 50% sheathing)
м.п.
275 ₴
21. From metal siding on metal posts
Name of work
Unit.
Cost
21.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
21.2. Cleaning of the food supply with rammers
м.п.
100 ₴
21.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
21.4. Formwork installation/dismantling
м.п.
205 ₴
21.5. Manufacturing of reinforcing cage
т
15 000 ₴
21.6. Concreting the foundation
м3
1 400 ₴
21.7. Concreting of free-standing pillars (if a strip foundation is not being made)
шт
350 ₴
21.8. Installation of fence guides in 2 rows
м.п.
100 ₴
21.9. Painting the fence
м.п.
150 ₴
21.10. Installation of metal siding
м.п.
300 ₴
22. From a chain-link mesh without a frame
Name of work
Unit.
Cost
22.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
22.2. Cleaning of the food supply with rammers
м.п.
100 ₴
22.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
22.4. Formwork installation/dismantling
м.п.
205 ₴
22.5. Manufacturing of reinforcing cage
т
15 000 ₴
22.6. Concreting the foundation
м3
1 400 ₴
22.7. Concreting of free-standing pillars (if a strip foundation is not being made)
шт
350 ₴
22.8. Installation of chain-link fencing
м.п.
200 ₴
23. From a chain-link mesh with a metal frame
Name of work
Unit.
Cost
23.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
23.2. Cleaning of the food supply with rammers
м.п.
100 ₴
23.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
23.4. Formwork installation/dismantling
м.п.
205 ₴
23.5. Manufacturing of reinforcing cage
т
15 000 ₴
23.6. Concreting the foundation
м3
1 400 ₴
23.7. Concreting of free-standing pillars (if a strip foundation is not being made)
шт
350 ₴
23.8. Manufacturing and installation of metal frames with chain-link fencing
м.п.
575 ₴
24. From 3D mesh
Name of work
Unit.
Cost
24.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
24.2. Cleaning of the food supply with rammers
м.п.
100 ₴
24.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
24.4. Formwork installation/dismantling
м.п.
205 ₴
24.5. Manufacturing of reinforcing cage
т
15 000 ₴
24.6. Concreting the foundation
м3
1 400 ₴
24.7. Concreting of free-standing pillars (if a strip foundation is not being made)
шт
350 ₴
24.8. Installation of 3D mesh
м.п.
425 ₴
25. From metal and forged elements
Name of work
Unit.
Cost
25.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
25.2. Cleaning of the food supply with rammers
м.п.
100 ₴
25.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
25.4. Formwork installation/dismantling
м.п.
205 ₴
25.5. Manufacturing of reinforcing cage
т
15 000 ₴
25.6. Concreting the foundation
м3
1 400 ₴
25.7. Concreting of free-standing pillars (if a strip foundation is not being made)
шт
350 ₴
25.8. Installation of a fence made of metal and forged elements
м.п.
3 850 ₴
26. Made of solid gabions
Name of work
Unit.
Cost
26.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
26.2. Cleaning of the food supply with rammers
м.п.
100 ₴
26.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
26.4. Formwork installation/dismantling
м.п.
205 ₴
26.5. Manufacturing of reinforcing cage
т
15 000 ₴
26.6. Concreting the foundation
м3
1 400 ₴
26.7. Installation of a gabion fence
м.п.
2 750 ₴
27. From gabions with wood filling between columns
Name of work
Unit.
Cost
27.1. Ritting trenches for pouring the foundation
м.п.
150 ₴
27.2. Cleaning of the food supply with rammers
м.п.
100 ₴
27.3. Arrangement of crushed stone bedding with tamping
м.п.
110 ₴
27.4. Formwork installation/dismantling
м.п.
205 ₴
27.5. Manufacturing of reinforcing cage
т
15 000 ₴
27.6. Concreting the foundation
м3
1 400 ₴
27.7. Installation of a gabion fence with wood filling between the columns
м.п.
2 850 ₴
28. From concrete slabs
Name of work
Unit.
Cost
28.1. Construction of a prefabricated fence made of concrete slabs
м.п.
600 ₴
29. Additional robots
Name of work
Unit.
Cost
29.1. Regular sliding gates
шт
10 000 ₴
29.2. Swing gates with automation
шт
9 000 ₴
29.3. Swing gates without automation
шт
7 000 ₴
29.4. Gate
шт
3 500 ₴
30. Dismantling works
Name of work
Unit.
Cost
30.1. Dismantling the gate
шт
5 000 ₴
30.2. Dismantling the gate
шт
1 750 ₴
30.3. Dismantling a prefabricated fence made of concrete slabs
м.п.
300 ₴
30.4. Dismantling a gabion fence
м.п.
1 350 ₴
30.5. Dismantling a fence made of metal and forged elements
м.п.
1 750 ₴
30.6. Dismantling the 3D mesh
м.п.
215 ₴
30.7. Dismantling the chain-link fencing
м.п.
100 ₴
30.8. Removing metal siding
м.п.
150 ₴
30.9. Dismantling the fence
м.п.
140 ₴
30.10. Dismantling corrugated sheets
м.п.
155 ₴
30.11. Dismantling the decorative block
шт
50 ₴
30.12. Dismantling a brick fence
м.п.
2 200 ₴
30.13. Dismantling a wooden fence
м.п.
405 ₴
30.14. Dismantling a fence made of concrete slabs
м.п.
290 ₴
1. Additional expenses
Name of work
Unit.
Cost
1.1. Loader services (price negotiable)
0 ₴
1.2. Delivery of materials (price negotiable)
0 ₴
1.3. Garbage removal (price negotiable)
0 ₴
1.4. Overhead costs (15% of the cost of work) https://rbk-alba.com/ua/blog/nakladnye-rasxody-cto-vklyucaet-v-sebya-eto-ponyatie
%
15 ₴
1.5. Designer and architect services (price negotiable)
0 ₴
1.6. Lawyer services (price negotiable)
0 ₴
1.7. Technical services (price negotiable)
0 ₴
1.8. Rental of premises for storing construction materials and tools (price negotiable)
0 ₴
1.9. Renting premises for the masters (price negotiable)
0 ₴
1.10. Registration of permits (price negotiable)
0 ₴